[MITgcm-devel] isomip verification experiment
Martin Losch
Martin.Losch at awi.de
Mon Oct 21 11:02:29 EDT 2013
Hi Jean-Michel,
I have no objections, go ahead
Martin
On Oct 21, 2013, at 4:59 PM, Jean-Michel Campin <jmc at ocean.mit.edu> wrote:
> Hi Martin,
>
> I would like to reduce the size of the tiles (to have more tiles)
> in both the forward and AD isomip set-up.
> thinking of changing to sNx,sNy=25,25, and changing SIZE.h_mpi
> to nPx,nPy=2,2.
>
> The main motivation would be to test MPI with more than 2 procs
> (and still have more than 1 tile per proc, since will still
> have nSy=2), and since this set-up is not too small (and tested
> with TAF & OpenAD), would be a good one.
>
> Do you agree with these changes ?
>
> Cheers,
> Jean-Michel
>
> _______________________________________________
> MITgcm-devel mailing list
> MITgcm-devel at mitgcm.org
> http://mitgcm.org/mailman/listinfo/mitgcm-devel